DocHub
Formula chain, equipment mappings, cost calculation logic, and override system

Calculation Engine

Purpose

The calculation engine (backend/src/services/calculator.ts) is the core of the application. It takes building block quantities from the PPS Space Calculator, looks up equipment mappings, applies regional pricing, and produces a 15-row cost summary table with Equipment, Installation, CAPEX, OPEX, and BAU columns.

Calculation Chain

  1. Space Aggregation — Sum building block quantities across all floors
  2. Data Points — Calculate total data points from low + high per block
  3. Tech Breakdown — Multiply block qty x equipment multiplier from building_block_equipment_map
  4. Network Design — Add site-size-specific network equipment from network_designs table
  5. Derived Items — Calculate Access Switches, cabling, cabinets from data point counts
  6. Security Items — Add CCTV from site size if scope includes it
  7. Equipment Overrides — Apply manual qty/cost overrides and add new items (2026-02-23)
  8. Category Totals — Sum equipment costs by category x regional unit prices
  9. Cost Summary — Build the 15-row table with formulas below
  10. Cost Overrides — Apply manual cell-level overrides to cost summary (2026-02-23)

Formulas (All Verified)

Line Formula Status
Installation 25% of Equipment Verified across 3 projects
CAPEX Equipment + Installation Verified
BAU 60% of CAPEX (10%/year x 6 years) Verified (fixed 2026-02-22)
ITO 10% of (Equipment + Installation) Verified
PMS Fee from site_sizes.pms_fee (varies by tier) Fixed 2026-02-22 — Craig provided 5-tier schedule
Design (AV/SCS) scs_design_cost from site_sizes, modified by Design Scope toggle Verified
WiFi Heatmap wifi_heatmap_cost if scope includes it Verified
PPS 2% of (Equipment + Installation) if over 5,000 Verified
Contingency MAX(5% of (Equipment + Installation), ,000) Under review — may be simpler flat K
LCR Year 6 90% of (Equipment + Installation) Implemented, not yet verified
Decommissioning Sum of (qty x multiplier x rate) per activity Implemented 2026-02-22 — verified 50 for Church Lane

PMS Fee Schedule (from Craig)

Project Size Tier PMS Fee
Mini 5,000
Small 5,876
Medium 11,752
Large 23,400
Extra Large 97,000

Craig can arbitrarily assign any tier to any project. The default is looked up by site_size_id.

Decommissioning Activities (9 types)

Activity Multiplier Rate/hr Cost per unit
Desk Decommissioning 1x 0 0/desk
AV/VC Decommissioning 8hrs 0 60/config
Removal of Wireless APs 1hr 0 0/AP
SER-Switch Unpatching 4hrs 0 80/switch
MTR Decommissioning 8hrs 0 60/rack
Vertical Fiber Primary 16hrs 0 ,120/route
Vertical Fiber Secondary 32hrs 0 ,240/route
Network Delivery Team 24hrs 25 ,000/team
End-user Services 24hrs 25 ,000/team

Only applies to Refurbishment, Relocation, Restack, and Decommissioning project scopes. Not applicable to New Build, ATM, or Design-only.

Scope Considerations (9 toggles)

Toggle Affects
Wireless AP WAP equipment inclusion
Security CCTV points
Structured Cabling All cabling items
Design Scope SCS and AV / SCS Only / AV Only / WiFi Only / All
Wi-Fi Heatmap WiFi heatmap design fee
Networks Network equipment (full or access switch only)
Voice Allowance Network Services OPEX
Servers Server cost from site size
Cabinets and Racks Cabinet equipment

Equipment Override System (2026-02-23)

Six retail/branch banking building blocks have zero auto-mappings. Rather than wait for Craig’s mapping data, a manual override system allows users to:

  • Override quantities — Change auto-calculated equipment qty for any item
  • Override unit costs — Change regional unit price for any item
  • Add new items — Insert equipment not in the reference data

Overrides are stored in project_equipment_overrides table and applied at step 7 in the chain. Items with overrides are flagged (is_overridden) in the tech breakdown output. See the Equipment & Cost Overrides page for full details.